On 29 June 2018, Madagascar was found to have made meaningful progress in implementing the EITI Standard.
Timeline of Validation and related materials
- 29 December 2019: Validation commenced
- 27-31 January 2020: Stakeholder consultations
- 19 March 2020: Draft Secretariat assessment sent to MSG
Secretariat assessment & comments
- 19 March 2020 - Draft Secretariat assessment
- 22 April 2020 - Comments from the MSG
- 8 May 2020 - Final Secretariat assessment
Validation Committee and Board review
- 2 June 2020 - VC Recommendation to the Board, Board Circular 291
- 9 June 2020 - Board decision 2020-30/BC-291, scorecard and corrective actions
Background
This is a second Validation. On 29 June 2018, the EITI Board found that Madagascar had made meaningful progress in implementing the EITI Standard (see Board decision 2018-35/BM-40). The Board established that progress in addressing fifteen corrective actions would be assessed in a second Validation starting on 29 December 2019.