Summary
The EITI work plan forms the foundation for all EITI activities in implementing countries and ensures that they are targeted to deliver the results desired by stakeholders. Based on the EITI Standard and EITI Principles, the multi-stakeholder group (MSG) should consult with stakeholders and review ongoing disclosure practice and national priorities to identify appropriate activities and results for EITI implementation. This process should link EITI implementation to key national priorities for the extractive industries and produce a work plan that can be actively used to strengthen implementation activities, document results and increase the impact of EITI implementation on national resource governance.
Requirement 1.5 of the EITI Standard sets out requirements for the contents of work plans. This note explains how this requirement can be implemented in more detail and proposes a five-step approach for how a work plan could be elaborated: (1) Organise and prepare, (2) Map and consult to identify priority issues, (3) Define objectives, activities, and scope (4) Approve and disseminate the work plan, and (5) Monitor and review. The note draws from experiences in national work planning and provides examples and suggestions for further reading.
Overview of steps
Steps | key considerations | examples |
---|---|---|
Step 1: |
|
|
Step 2: |
|
|
Step 3: |
|
|
Step 4: |
|
|
Step 5: |
|
|
How to implement Requirement 1.5
Step 1: Organise and prepare
Developing a results-oriented work plan which reflects views from key stakeholders requires time and effort, but has important benefits related to stakeholder engagement, learning and accountability, as described at the beginning of this Guidance Note. To organise and prepare the work planning process, MSGs could consider the following steps:
- Identify who will be responsible for developing the work plan. Many MSGs appoint an ad hoc working group or assign this work to an MSG Standing Committee to conduct consultations, prepare documents and facilitate MSG discussion and endorsement of the work plan. Such groups should be composed of members of the national secretariat and at least one representative of each MSG stakeholder group.
MSGs may also want to consider using independent consultants to support work plan development. This is an opportunity to bring diversity of background and expertise within the MSG. The EITI International Secretariat can suggest consultants with appropriate capacity and expertise, who can help to design and coordinate processes for developing a work plan.
- Plan and communicate appropriate timeframes. Developing a robust work plan can be time consuming and require several workshops and consultations to arrive at agreement. It is not unusual that these processes can take several months. Plan accordingly when allocating time and resources to the work planning process, and ensure that development and approval of the work plan is aligned with budget and funding cycles for the MSG.
Colombia: Structuring and planning the work planning process
Colombia’s 2020-2023 work plan was developed through a three-step process and presents a plan and specific roles to carry out consultations:
- A technical subgroup of the MSG consulted MSG members to assess current governance and disclosure practice in the extractives sector and to develop trend scenarios.
- Stakeholder related to extractive mining activities but not represented on the MSG were consulted to identify their needs and perspectives in relation to EITI implementation.
- The MSG Technical Secretariat reviewed the results from steps 1 and 2, to identify possible modes of implementation, including activities with specific lines of responsibility.
Step 2: Identify priority issues
For the EITI to be an effective intervention, it must be relevant. EITI implementation must demonstrate how it contributes to existing goals and efforts and meets specific needs to strengthen natural resource governance. This should begin with a review of existing disclosures and disclosure gaps relative to the EITI Standard, followed by a broad and inclusive consultation with stakeholders to identify national priorities in the extractive sector. This information can then be used to define the overall objectives for the EITI work plan.
-
Review current disclosure and implementation practice. A review of existing disclosures can help to identify weak points and bottlenecks that should be addressed in the work plan. It can also be important to identify what types of data are and are not systematically disclosed and where this can be strengthened. MSGs may use the Transparency template as a tool to for this mapping, which will also help MSGs to prepare for annual reporting and Validation.
Recommendations from previous Validations and EITI reporting can also provide insight on weaknesses or gaps in disclosure and implementation. In addition to this preparatory mapping, MSGs could consider conducting a systematic disclosure mapping, feasibility study and thematic scoping studies to inform these discussions, and including such efforts as a specific activity in work plans.
-
Review national priorities. A review of current disclosure practices should be complemented by review of national priorities related to extractive sector governance. Several sources can be helpful in identifying national priorities. Though an exhaustive mapping might not be feasible, MSGs may consider consulting the following sources to inform this review:
-
Government (national and subnational) policies or strategies for the extractive sector, public debates about issues in the extractive sector, and analysis and research undertaken by government, media, NGOs, companies or other institutions.
-
Existing reform efforts aimed at improving extractive sector governance in the country, and how the EITI may be linked operationally or financially to these efforts.
-
International commitments, for example to international development banks and institutions, or other multi-stakeholder initiatives such as the Open Government Partnership (OGP).
-
Recent external reports and studies on the sector conducted by civil society, industry or international development actors such as the World Bank or IMF.
-
The national priorities identified in this exercise might reflect specific aspects of resource governance in the EITI Standard, such as contract transparency (Requirement 2.4) or beneficial ownership disclosure (Requirement 2.5). National priorities might also include long-term national objectives related to the energy transition, the national investment climate, or the resilience of government systems for revenue collection. The relevance of such issues for EITI implementation can be clarified in consultations with stakeholders.
Suriname: Aligning the work plan with national priorities
Suriname’s 2019-2020 work plan describes several national policy issues that inform the formulation of the work plan’s objectives and activities. This includes national development plans endorsed by parliament, relevant legislation, ministerial engagement with international financial institutions, and lessons learned from implementation and review. The work plan’s activities are preceded by a review of results and progress on each activity from the preceding work plan, providing an opportunity to link ongoing work across annual work plans, and how those relate to national priorities.
3. Identify key stakeholders and stakeholder groups. Stakeholder consultations are an essential foundation for EITI work plans and can increase their legitimacy and impact. The first and core point of consultation is often situated within the MSG. However, all key stakeholders might not be represented on the MSG so it is important for each constituency on the MSGs to establish and maintain consultation channels with external constituency representatives.
It may also be helpful to consider what other groups are important to consult, including highly impacted groups, such as women’s rights organisations and marginalised communities. To do so, consider recommendations and findings from Validations or EITI Reports and feedback from dissemination activities, as well as literature on the social impacts of the extractive industries in the country, gender analyses or human rights reports that address issues such as structural inequality or discrimination against relevant stakeholder groups. This consideration will help the MSG provide a national priority-led work plan that accounts for the communities affected by the sector.
In addition to considering affected stakeholders, consultations should engage stakeholders that support EITI implementation, particularly when they play a role in the systematic disclosure and use of extractives data. Submitting the work plan for consultation to a wider range of stakeholders (including development partners) may also be key to ensuring that the EITI does not operate in a silo, and that information collection is not duplicated (e.g. reporting on legal owners of extractive companies).
Taking the steps above helps stakeholders have real influence on work planning. MSGs may also consider how they can communicate this feedback process to stakeholders in a way that builds legitimacy and engagement for meaningful EITI implementation.
Indonesia: Stakeholder engagement planning
Indonesia has complemented its work plan with a dedicated “Stakeholder Engagement Plan” to facilitate mainstreaming efforts by the Indonesian MSG. This includes specific tools for planning stakeholder engagement, such as the “importance and influence matrix” presented below.
4. Identify appropriate mechanisms for consultations. Consultation mechanisms may include national or regional workshops, an active and open invitation to all citizens through national and local media, or specific consultations with relevant ministries, organisations, networks or coalitions. MSGs may also consider the following aspects:
- Online or offline: Depending on national context and accessibility, consider whether consultations should be held online to be more accessible to stakeholders that may not be able to travel, or whose participation might be limited by restrictions related to the COVID-19 pandemic. MSGs could consider using mobile and social media platforms to engage more remote groups.
- Real-time dialogue or open mailbox: Convening stakeholders for in-person or virtual discussion can allow for productive dialogue and exchange, but it can also limit the number of stakeholders who are able to contribute meaningfully. Having an open period where stakeholders can submit inputs to a post address, email address or online survey can increase the number and quality of inputs.
- Timeframes: Consultations should be designed so that stakeholders have enough time to familiarise themselves with the EITI process and make meaningful contributions. This means giving advance notice of scheduled consultations and ensuring that the period for open comment is long enough to allow for maximum participation (e.g. two weeks).
- Co-create: Ask stakeholders what they would like to see prioritised in the work plan. Ensure that consultations give an opportunity to provide inputs relating to priorities for EITI implementation in the coming year. It may also be helpful to ask stakeholders about how they would want to access and use EITI data and information. This could help the MSG understand how to increase the potential for public debate and use of data in accordance with Requirement 7 and as reported in the Outcomes and impact template for EITI Validation.
- Feedback: Consultations should also provide information about how the inputs received will feed into the EITI work plan. This means sharing consultation results with participants and informing them about how consultations led to work plan changes. This can be achieved through specific consultations, or regular monitoring processes as described in Step 5.
There is no single perfect format for stakeholder consultations, and the best solution is likely a combination of the options above. In determining the platforms and mechanisms for consultations, MSGs should ensure that these are communicated to all relevant stakeholders with advance notice and clear instructions on how to participate. Keeping platforms open for continued input during work plan implementation will also help to strengthen stakeholder engagement and the legitimacy of EITI implementation.
Survey template to identify national priorities and EITI objectives
The EITI International Secretariat developed a model survey to help countries identify national priorities and objectives for EITI implementation. The survey can be used to gather views from MSG members and wider stakeholders on the challenges of the sector, and what they think should be the focus areas of the EITI. The responses can serve as a starting point of a workshop series. The survey questions can be changed. An Office 365 license is required to use the tool.
Access and copy the model survey here.
Democratic Republic of the Congo: Review processes for work planning
The DRC’s 2018-2021 was based on rigorous process of review and consultation. This began with two self-assessment processes in which the MSG looked at their implementation in accordance with the EITI Standard and identified gaps. These assessments supported additional analysis and recommendations from independent consultants. The joint inputs were used to convene a workshop, in which stakeholders reviewed and prioritised activities, linking them to national priorities.
5. Define national priorities and work plan objectives. The EITI Standard requires work plans to include objectives that are linked to the EITI Principles and reflect national priorities for the extractive industries.
The process of selecting and defining objectives for the work plan should be grounded in stakeholder consultations, a mapping of disclosures and a review of national priorities that have already been undertaken. MSGs may also wish to emphasise systematic disclosure of EITI information, issues raised in recommendations from Validation and reporting or feasibility studies, or objectives related to overcoming constraints or obstacles to EITI implementation.
Objectives for the EITI work plan should be concise and specific. They should reflect what EITI implementation can reasonably be expected to achieve or contribute to in the period covered by that work plan. Objectives will thus be less ambitious than the national priorities to which they are related. Having a small number of objectives (five or less) may make it easier to plan activities and achieve results.
When formulating objectives, it can be helpful to describe how they link to national or stakeholder priorities or identify weaknesses in systematic disclosure and EITI implementation. Consider complementing the objectives with a short narrative explaining these connections. Objectives may also link to more specific outcomes that are prioritised by specific stakeholders.
Albania: Targeting systematic disclosure to support institutional outcomes
Albania’s 2016-2019 work plan features mainstreaming and systematic disclosure as a key objective. This objective is aligned with national strategies for digitalisation and e-governance as well as the national open data policy and open data portal. The objective is rationalised as supporting a variety of institutional outcomes, including “to ensure timeliness, data quality, reuse and cost effectiveness.”
Papua New Guinea: Framing and linking work plan objectives
The Papua New Guinea 2021 work plan is organised around five distinct objectives:
- Ensuring a well-established and fully functional national secretariat office and MSG;
- Show the extractive industries’ contribution (both direct and indirect) to the PNG economy;
- Improve public understanding of extractive sector management;
- Strengthen revenue generation and collection that is consistent with government policy setting and national development priorities;
- Endeavor to fully implement PNGEITI Report recommendations as directed by Cabinet.
Each of these objectives is presented with a rationale linking to national priorities, a short description of related governance challenges, and a set of activities that are measurable, time-bound, costed and designed specifically to achieve that objective.
Nigeria: Aligning the work plan to national priorities
Nigeria’s 2019 narrative work plan identifies nine work plan objectives reflecting four strategic goals for EITI implementation for 2017 to 2019. These are based on three core national priorities for Nigeria: Corporate governance and anti-corruption, economic diversification and sustainable economic development.
This framing helps the Nigeria EITI work plan to draw a clear link between implementation activities for that year and high-level national priorities, as illustrated below:
National priority |
Corporate governance and anti-corruption |
Long term EITI strategic goal |
Strategic Goal 1: Deepen openness in the extractive sector through timely audits and other impactful studies |
Work plan objective |
Achieve regular audits reporting of the extractive industries sector, automate NEITI data gathering process and implementation of remediation issues from the audit. |
Activity |
Scoping study for 2017 Oil and Gas Audit and template review for Oil and Gas Report |
Mauritania: Presenting the relationship between different goals and priorities
To conceptualise the complex relationships between different national priorities and objectives relevant to EITI and work planning, the Mauritania 2021 work plan visualises how EITI outputs align with national priorities to shape the context for achieving Mauritania’s national development goals.
Step 3: Define work plan objectives, activities and scope
According to the EITI Standard, the work plan must “include measurable and time-bound activities to achieve the agreed objectives. The scope of EITI implementation should be tailored to contribute to the desired outcomes and impact that have been identified during the consultation process.” (EITI Requirement 1.5.c).
- Identify activities that will contribute to the work plan objectives. Sometimes it will be obvious which activities are necessary to achieve objectives in the EITI work plan. In most cases, undertaking an EITI Report would fall under this category. This will not always be the case, however, and identifying appropriate activities to achieve work plan objectives might require strategic discussion or brainstorming with stakeholders. This can be incorporated into the stakeholder consultations described above or conducted by MSG working groups.
- Identify activities that will address other issues required by the EITI Standard. In addition to activities directly addressing work plan objectives, work plans should include activities that respond to specific issues required by the EITI Standard, including:
- Activities to strengthen systematic disclosures and technical aspects of disclosures, such as comprehensiveness and data reliability (Requirements 4.1 and 4.9);
- Activities to reflect frontier and crosscutting themes, such as anti-corruption, energy transition and domestic resource mobilisation;
- Activities to increase the disclosure of contracts in accordance with Requirement 2.4 and beneficial ownership information in accordance with Requirement 2.5, including milestones and deadlines that might be captured in a beneficial ownership disclosure roadmapHideSee EITI (2016), Guidance Note: EITI Requirement 2.5 (planning for beneficial ownership disclosure) and “Advisory checklist for EITI beneficial ownership roadmap”;
- Plans for communicating and disseminating EITI data, with special attention to subnational data, that take into account various levels of access, especially by women, minority and other potentially marginalised groups (Requirements 7.1 and 7.2). These are discussed further in Step 5 below; and
- Activities to overcome capacity constraints in government agencies, companies and civil society (expertise, data gaps, capacity, finances, legal, administrative) that may affect implementation of the work plan (Requirement 1.5 (c) i).
Zambia: Linking activities, indicators and impacts
One of the four objectives in Zambia’s 2021-2022 work plan is to “support routine systematic disclosures of comprehensive and reliable EITI information by Government and Mining Companies.” As with all objectives in the work plan, this objective is presented together with intermediate outcomes related to changes of performance and capacity, and multiple outputs, each of which are supported by multiple activities, as shown for the outputs 3 and 4 below:
Ultimate outcome |
Improved government reform resulting in increased mainstreaming of information on the extractives |
|
Intermediate outcomes |
Improved compliance with the EITI Standard and EITI Requirements |
|
Immediate outcomes |
Strengthen ZEITI to implement and meet EITI Requirements |
|
Output |
3.0 - ZEITI internal training and skills development |
4.0– Gender mainstreaming and training |
Activities |
3.1– ZEITI Secretariat online training leadership, organisational management, software and communications 3.2 ZEITI Secretariat fundraising and proposal writing 3.3 ZEC- ZEITI Secretariat training: Mine life cycle/ASM life cycle/petroleum 3.5 ZEC- ZEITI Secretariat training: Mining taxation 3.6 ZEC- ZEITI Secretariat training: Other to be identified |
4.1 Oxfam gender awareness raising and training 4.2 Webinar roundtable on gender dynamics for MSG 4.3 Development of gender policy/strategy 4.4 Implement gender policy/strategy |
3. Define activities in a way that is measurable and time-bound. One effective way of ensuring this is to apply the SMART criteria: Specific, Measurable, Achievable, Relevant, Time-boundHideThere are many sources of online information regarding the SMART criteria. For a presentation in the context of EITI implementation, see GIZ (2017), Monitoring and Evaluation (M&E) of EITI Implementation - Guideline. Most importantly, each activity should have a timeframe for implementation. The timeframe should consider the deadlines established by the EITI Board for producing EITI Reports, annual activity reports and Validation. In developing the timetable, the MSGs should also consider administrative requirements such as procurement processes and funding. Work plans should also estimate the cost of each activity and how they will be funded. As a dynamic document, MSGs have and can revise work plan activities where necessary (e.g. to respond to challenges brought by the COVID-19 pandemic).
It is also important to consider assigning responsibilities to relevant stakeholders for each activity. This may, in some cases, require involvement of stakeholders beyond those represented on the MSG (e.g. activities related to beneficial ownership disclosure), and consultation with such stakeholders might be necessary. In some countries, an assessment of integrating multi-stakeholder consultation and oversight into existing representative bodies may be usefulHideSee EITI (2021), Guidance Note: EITI Requirements 1.4 (multi-stakeholder groups). Equally important, MSGs should consider frequently assessing the feasibility (i.e. financial, capacity) and impact (i.e. timing, opportunity, needs) of work plans activities and revise these where necessary (e.g. to respond to challenges brought by the COVID-19 pandemic). This will help ensure a good balance between consistency and redundancy.
4. Identify appropriate targets for activities. Consider what kinds of results might follow from activities and define measurable and time-bound indicators for when those results should be achieved. This will help to monitor the work plan and strengthen its implementation. Also, consider who benefits from these activities, and whether they are inclusive and gender-responsiveHideGender-responsiveness refers to outcomes that reflect an understanding of gender roles and inequalities and which make an effort to encourage equal participation and equal and fair distribution of benefits. Gender responsiveness is accomplished through gender analysis and gender inclusiveness. For more information, see UNDP (2015), Gender Responsive National Communications Toolkit , where relevant.
When identifying targets, MSGs could consider the relationship between activities, work plan objectives, and national priorities using a logical framework approach. This involves considering the sequence and causal relationships between inputs and activities, outputs, outcomes and impacts.
Linking work plan activities to inputs, outputs, outcomes and impacts
The table below exemplifies these links in a results chain in the first column. The second column notes how they might be reflected in national priorities, work plan results and work plan activities. The third column illustrates how this was conceptualised in Senegal’s 2021 work plan.
link in the results chain | level of results | articulation in Senegal's 2021 work plan |
---|---|---|
Impacts: |
National priorities |
Impact: the effectiveness of good governance and transparency in management of the extractive industries |
Outcomes: Changes to policy, behaviour, beliefs |
Work plan results |
Effect: Operationalisation of transparency mechanisms, with a view to establishing optimal governance Immediate result: Better knowledge of the extractive sector by citizens |
Outputs: Documents, workshops, media |
Work plan results and activities |
Output: Creation of an environment conducive to transparency in extractive governance by strengthening access to information, the impetus for reforms and capacity building of actors |
Inputs: |
Work plan activities |
Activity: Implement the EITI process in Senegal |
5. Write a narrative text to present the work plan. Once objectives and activities are decided, a smaller MSG subcommittee or working group may be tasked with drafting the narrative work plan to make it more accessible and operationally useful. This work should clearly represent the objectives, scope, activities and targets described above, in a manner that is easily accessible for stakeholders. Additionally, it is important to ensure that several other components required by the EITI Standard are included:
- A description of who was involved in the consultative and review processes in Step 1, and how stakeholder views and priorities were considered.
- A list of sources reviewed to identify national priorities, including links to sources.
- An overview of domestic and external sources of funding and technical assistance where appropriate in order to ensure timely implementation of the agreed work plan. This should include funding for specific activities as described in Step 3, but also more general funding for MSG operations and EITI implementation.
- A description of specific plans for disseminating and monitoring the work plan as described in Steps 5 and 6 below.
- A timetable for implementation that is aligned with the deadlines established by the EITI Board in accordance with Section 4 of the EITI Standard, and that takes into account administrative requirements such as procurement processes and funding.
Democratic Republic of the Congo: Presenting a complete and actionable work plan
The DRC’s 2018-2021 work plan has two parts:
- A narrative which describes the process in which the work plan was developed. It also presents the work plan objectives, and the activities and risks that were associated with each. This provides context and legitimacy for the logical framework that follows.
- A logical framework, which presents each activity in a table alongside corresponding objectives, expected results, responsible parties, timeframes, costs and funding sources.
Step 4: Endorse and disseminate the work plan
- Endorse the work plan. Once a final draft of the work plan is prepared, it must be endorsed by the MSG (Requirement 1.5.b).
- Disseminate to maximise accessibility and feedback. The MSG should make the work plan widely available to the public, as required by the EITI Standard. This may include publishing the work plan on the national EITI website and/or other relevant ministry and agency websites, or in print media or other places that are easily accessible to the public, and sharing it with those consulted. Ideally, the most appropriate places for dissemination will have been identified during stakeholder consultations. Specific measures to publicise the work plan should be identified, taking into consideration:
- Whether the work plan should be translated and printed in local languages;
- Whether the work plan can be graphically represented to be easier to read and understood;
- What combination of print or online formats is necessary to ensure accessibility, in cases where this is limited internet access and media literacy;
- Specific mechanisms or communication channels through which stakeholders can provide feedback or input to the work plan during implementation.
The MSG may wish to consider alternative or complementary formats and platforms for the work plan that make it easy to use, monitor and revise. This may involve the use of spreadsheets, tables, Gantt charts or other formats.
Philippines: Publishing work plans and progress matrices online
The Philippines EITI (PH-EITI) website presents current and past work plans, together with progress matrices that track implementation of work plan activities on a running basis. The 2021 work plan also contains a detailed narrative description of how the work plan was elaborated and explains the issues that PH-EITI aims to address, the rationale behind the objectives, the planned activities, and how the different elements of the EITI process link to other reform efforts.
Indonesia: Stakeholder engagement planning
Indonesia’s Stakeholder Engagement Plan (SEP) is designed to facilitate mainstreaming efforts by Indonesia’s MSG. This includes dedicated activities to secure feedback on the EITI work plan, and the SEP is presented as “a living document [that will be] periodically updated during project implementation to reflect any adjustment made based on the changing contextual factors or new information related to the stakeholder engagement.”
Step 5: Monitor and review
The work plan is a living document, which should be reviewed and updated frequently to make it a useful management tool, and to anchor its legitimacy and usefulness as an accountability tool for stakeholders.
- Establish a schedule for review. The work plan must be reviewed and updated annually according to Requirement 1.5 (f). Many countries also align new work plans with budgetary processes. Regardless of the planning cycle, a work plan must be reviewed at least once per year, and MSGs are advised to consider more regular updates and revisions. The MSG could, for example, agree to briefly revisit the work plan during each of its quarterly meetings to take stock of progress.
Revising the work plan is also essential to reflect lessons learned and integrate the recommendations for improvement by Independent Administrators or Validation reports. It may be helpful to update the work plan following the publication of the EITI Report and Validation.
Armenia: Quarterly progress reporting to stakeholders
The Armenia EITI MSG prepares quarterly progress reports describing the implementation of activities set forth in the work plan. Stakeholders consulted during the Validation process described these reports as useful tools to track progress and adjust activities if needed.
2. Consider developing a monitoring, evaluation and learning framework. MSGs may wish to consider developing a more regular framework for monitoring, evaluating and learning (MEL) from implementation of the EITI work plan. Having a robust and specific MEL framework can help MSGs to adapt work plans and activities during implementation, improving the results of implementation and making it easier to communicate the EITI’s impact. A strong MEL framework can also boost credibility with national and international partners and donors.
Developing an MEL framework may require relatively little effort if work plans are conceptualised with strong links between activities and outcomes, and if they incorporate measurable and time-bound indicators as described in Step 3.
Guideline for Monitoring and Evaluation (M&E) of EITI Implementation
GIZ has produced a guideline that seeks to complement EITI guidance that covers aspects of monitoring and evaluation (M&E). It offers a practical overview of many of the issues highlighted in this Guidance Note, and practical, step-by-step guidance for how to develop an M&E framework, such as measures to build agreement on definitions, processes and resource management, including suggestions for workshops and data collection.
Senegal: Integrating monitoring and evaluation into work planning
Senegal’s 2021 work plan includes the implementation of a monitoring and evaluation process to be managed by a technical commission dedicated to capacity building and M&E. This involves the regular review of key performance indicators included in the work plan’s logistical framework, and the use of several tools to track and report on progress, including dashboard indicators, a monitoring-evaluation matrix, and the release of a progress report twice annually. The commission is further mandated to consult stakeholders beyond the MSG when assessing and reporting on progress, including the involvement of parliamentarians and women’s groups. This is planned according to weekly, quarterly, bi-annual and annual activities.
Ukraine: Building M&E into work planning
Ukraine’s 2021 work plan is presented in the form of a logistical framework. It includes instructions for monitoring activities to be executed by the national secretariat or other responsible parties every two months and specifies that implementation progress will be discussed at each MSG meeting.
The work plan builds on Ukraine’s dedicated M&E framework which distinguishes between evaluation activities focused on impacts and outcomes, and monitoring activities focused on the same. The framework also includes a monitoring table to track progress over time, shown below.
3. Devote time to meaningful and inclusive reflection. Whether work plans are reviewed annually, more regularly, or as part of a structured MEL process, MSGs and national secretariats are encouraged to convene a broad collection of stakeholders and allocate sufficient time to review and reflect on how the work plan has been implemented. Some useful questions to prompt reflection might include:
- Which results were achieved?
- Which results were not achieved, and why not?
- What could have been done differently?
- Were the assumptions correct about how activities would contribute to specific results, to contribute to work plan objectives and national priorities?
- What could be done differently now, and in the next work plan?
- What are the activities that we carry over to the next year
- Were any positive results achieved that were not described in the work plan?
MSGs and national secretariats may also wish to use the Outcomes and Impacts template when reviewing work plans. Doing so can help to prepare for Validation processes, and provide a useful format to structure review processes.
4. Ensure that review informs subsequent work planning. The outcomes of review processes should be captured in such a way that they can be reviewed in future work planning, as described in Step 2. It might be helpful to think of the review process as the link between successive work plans in the EITI annual disclosure cycle, illustrated below.
To ensure that work plan review feeds directly into later work planning processes, it may be helpful to produce public statements or documents summarising the work plan review process. MSGs may also wish to consider regularly publishing a logical framework (logframe) or spreadsheets that are produced during MEL processes. The EITI International Secretariat can support in facilitating a review and planning workshop for work plans.
Further resources
- EITI (2021), “2021 Validation model templates”
- EITI (2021), Guidance Note: EITI Requirement 1.4 (multi-stakeholder groups)
- EITI (2016), Guidance Note: EITI Requirement 7.3, 7.4 and 1.5
- GIZ (2017), Monitoring and Evaluation (M&E) of EITI Implementation – Guideline
- UN Development Programme (2015), Gender Responsive National Communications Toolkit