Skip to main content

The Board agreed that Niger has made inadequate progress overall in implementing the 2016 EITI Standard.

Decision on the outcome of Niger's Validation

Decision reference
2017-56 / BM-38
Decision basis
2016 EITI Standard, Requirement 8.3 EITI Validation deadlines and consequences

Board decision

The Board came to the following decision regarding Niger's status:

The Board agrees that Niger has made inadequate progress overall in implementing the 2016 EITI Standard. The Board’s determination of Niger’s progress with the EITI’s requirements is outlined in the assessment card below.

With respect the requirement 1.3 regarding civil society participation, the EITI Board used its discretion to consider events subsequent to the commencement of Validation. The Board noted that the situation had deteriorated significantly between March and September 2017. The Board concluded that there was not an enabling environment for civil society participation, and that Niger was no longer adhering to the civil society protocol. Therefore, Niger was assessed as having made “inadequate progress”.

In addition, areas of concern relate to industry engagement (1.2), governance of the multi-stakeholder group (1.4), work plan (1.5), legal framework (2.1), license allocations and register (2.2 and 2.3), policy on contract disclosure (2.4), state participation (2.6), production data (3.2), comprehensiveness (4.1), barter agreements (4.3), state-owned enterprises transactions (4.5), direct subnational payments (4.6), data quality (4.9), revenue management and expenditures (5.1), subnational transfers (5.2), mandatory social expenditures (6.1), quasi-fiscal expenditures (6.2) economic contribution (6.3), public debate (7.1) and outcomes and impact of implementation (7.4).

Accordingly, the EITI Board agreed that Niger will need to take corrective actions outlined below. Progress with the corrective actions will be assessed in a second Validation commencing on 26 April 2019. In accordance with the EITI Standard, Niger’s MSG may request an extension of this timeframe, or request that Validation commences earlier than scheduled.

The Board’s decision followed a Validation that commenced on 1 November 2016. In accordance with the 2016 EITI Standard, an initial assessment was undertaken by the International Secretariat. The findings were reviewed by an Independent Validator, who submitted a draft Validation report to the MSG for comment. The MSG’s comments on the report were taken into consideration by the independent Validator in finalising the Validation report and the independent Validator responded to the MSG’s comments. The final decision was taken by the EITI Board.

Corrective actions and strategic recommendations

The EITI Board agreed the following corrective actions to be undertaken by Niger. Progress in addressing these corrective actions will be assessed in a second Validation commencing on 26 April 2019:

  1. In accordance with requirement 1.2, companies should demonstrate that they are fully, actively and effectively engaged in the EITI process. In accordance with requirement 8.3.c.i, the company constituency is requested to develop and disclose an action plan for addressing the deficiencies in company engagement documented in the initial assessment and validator’s report within three months of the Board’s decision, i.e. by 26 January 2018.
     
  2. In accordance with requirement 1.3.c, the government must ensure that there are no obstacles to civil society participation in the EITI process. For the suspension to be lifted, the government should ensure that the civil society protocol is fully adhered to, including ensuring that civil society representatives are able to engage in public debate related to the EITI process and express opinions about the EITI process without restraint, coercion or reprisal.
     
  3. In accordance with requirement 1.4.a.ii, the MSG should ensure that its procedures for nominating and changing multi-stakeholder group representatives are public and confirm the right of each stakeholder group to appoint its own representatives. In accordance with requirement 1.4.b.ii and 1.4.b.iii, the MSG should undertake effective outreach activities with civil society groups and companies, including through communication such as media, website and letters, informing stakeholders of the government’s commitment to implement the EITI, and the central role of companies and civil society. Members of the MSG should liaise with their constituency groups. In accordance with requirement 1.4.b.vi, the MSG should ensure an inclusive decision-making process throughout implementation, particularly as concerns industry and civil society.
     
  4. In accordance with requirement 1.5.a, the MSG should maintain a current work plan that sets EITI implementation objectives that reflect national priorities for the extractive industries. In accordance with requirement 1.5.b, the work plan must reflect the results of consultations with key stakeholders. In line with requirement 1.5.c, the work plan must assess and outline plans to address any potential capacity constraints, identify and outline plans to address any potential legal or regulatory obstacles to EITI implementation, and outline the multi-stakeholder group’s plans for implementing the recommendations from Validation and EITI reporting. In accordance with requirement 1.5.f, the work plan must be updated annually.
     
  5. In accordance with Requirement 2.1.a, Niger must disclose a description of the legal framework and fiscal regime governing the extractive industries. This information must include a summary description of the fiscal devolution, an overview of the relevant laws and regulations, and information on the roles and responsibilities of the relevant government agencies.
     
  6. In accordance with requirement 2.2.a, Niger should ensure annual disclosure of which mining, oil, and gas licenses were awarded and transferred during the year under review, highlighting the technical and financial requirements and any non-trivial deviations from the applicable legal and regulatory framework governing license awards and transfers.
     
  7. In accordance with requirement 2.3, Niger should also ensure that the license holder names, dates of application, award and expiry, commodity(ies) covered and coordinates for all oil, gas and mining licenses held by material companies are publicly available.
     
  8. In accordance with requirement 2.4, Niger is required to document the government’s policy on disclosure of contracts and licenses that govern the exploration and exploitation of oil, gas and minerals through the EITI Report. This should include relevant legal provisions, any reforms that are planned or underway as well as an overview of contracts already published.
     
  9. In accordance with requirement 2.6, the MSG should provide an explanation of the prevailing rules and practices related to SOEs’ retained earnings and reinvestment. The government should also ensure annual disclosure of any changes in government ownership in SOEs or their subsidiaries, and provide a comprehensive account of any loans or loan guarantees extended by the state or SOEs to mining, oil, and gas companies.
     
  10. In accordance with requirement 3.2, the MSG should ensure future EITI Reports provide disaggregated production volumes and values for all key minerals produced in the year(s) under review.
     
  11. In accordance with requirement 4.1.a, Niger ensure that the materiality thresholds for selecting companies and revenue streams for reconciliation ensures that the exclusion of companies or revenues does not significantly affect the comprehensiveness of the EITI Report. The MSG is invited to consider whether setting a quantitative materiality threshold for selecting companies would ensure these aims are met. Niger should ensure that future EITI Reports clearly include all revenue streams listed under requirement 4.1.b in the scope of reconciliation. In accordance with requirement 4.1.c, the MSG should also ensure that the Independent Administrator assesses the materiality of non-reporting companies and government entities as well as provide its opinion on the comprehensiveness of the EITI Report. In accordance with requirement 4.1.d, the government should also ensure that future EITI Reports include aggregate information about the amount of total revenues received from each of the benefit streams agreed in the scope of the EITI Report.
     
  12. In accordance with requirement 4.3, the MSG and the Independent Administrator are required to consider whether there are any agreements, or sets of agreements involving the provision of goods and services (including loans, grants and infrastructure works), in full or partial exchange for oil, gas or mining exploration or production concessions or physical delivery of such commodities. Where the MSG concludes that these agreements are material, the MSG and the Independent Administrator are required to ensure that the EITI Report addresses these agreements, providing a level of detail and transparency commensurate with the disclosure and reconciliation of other payments and revenues streams. Where reconciliation of key transactions is not feasible, the MSG should agree an approach for unilateral disclosure by the parties to the agreement(s) to be included in the EITI Report.
     
  13. In accordance with requirement 4.4, the MSG should assess the materiality of any transportation revenues and disclose such revenues should they be assessed as material.
     
  14. In accordance with requirement 4.5, the MSG must ensure that the reporting process comprehensively addresses the role of SOEs, including material payments to SOEs from extractives companies, and transfers between SOEs and other government agencies.
     
  15. In accordance with requirement 4.6, it is required that the MSG establish whether direct payments from companies to subnational governments, within the scope of agreed revenue streams, are material. Where material, the MSG must ensure that direct company payments to subnational government entities are disclosed and reconciled in future EITI Report.
     
  16. In accordance with Requirement 4.9.a, the EITI requires an assessment of whether the payments and revenues are subject to credible, independent audit, applying international auditing standards. In accordance with requirement 4.9.b.iii and the standard Terms of Reference for the Independent Administrator agreed by the EITI Board, the MSG and Independent Administrator should:
  1. examine the audit and assurance procedures in companies and government entities participating in the EITI reporting process, and based on this examination, agree what information participating companies and government entities are required to provide to the Independent Administrator in order to assure the credibility of the data in accordance with Requirement 4.9. The Independent Administrator should exercise judgement and apply appropriate international professional standards[1] in developing a procedure that provide a sufficient basis for a comprehensive and reliable EITI Report. The Independent Administrator should employ his/her professional judgement to determine the extent to which reliance can be placed on the existing controls and audit frameworks of the companies and governments. The Independent Administrator’s inception report should document the options considered and the rationale for the assurances to be provided.
     
  2. ensure that the Independent Administrator provides an assessment of comprehensiveness and reliability of the (financial) data presented, including an informative summary of the work performed by the Independent Administrator and the limitations of the assessment provided.
     
  3. ensure that the Independent Administrator provides an assessment of whether all companies and government entities within the agreed scope of the EITI reporting process provided the requested information. Any gaps or weaknesses in reporting to the Independent Administrator must be disclosed in the EITI Report, including naming any entities that failed to comply with the agreed procedures, and an assessment of whether this is likely to have had material impact on the comprehensiveness and reliability of the report.
  1. In accordance with requirement 5.1.a, the MSG should ensure that the allocation of extractives revenues not recorded in the national are explained, with links provided to relevant financial reports as applicable.
     
  2. In accordance with requirement 5.2.a, the MSG should assess the materiality of subnational transfers prior to data collection and ensure that the specific formula for calculating transfers to individual local governments be disclosed, to support an assessment of discrepancies between budgeted and executed subnational transfers.
     
  3. In accordance with requirement 6.1.a, the MSG should agree a clear distinction between mandatory and voluntary social expenditures prior to data collection and ensure that material mandatory social expenditures are comprehensively disclosed in future EITI Reports. Where beneficiaries of mandatory social expenditures are a third party, i.e. not a government agency, the MSG should ensure that the name and function of the beneficiary be disclosed.
     
  4. In accordance with requirement 6.2, the MSG should consider the existence and materiality of any quasi-fiscal expenditures undertaken by extractives SOEs and their subsidiaries, ensuring that all material quasi-fiscal expenditures are disclosed in future EITI Reports.
     
  5. In accordance with requirements 6.3, the MSG should ensure that future EITI Reports provide the contribution of the mining, oil and gas sectors to GDP in absolute terms and an estimate of informal sector activity (6.3.a) as well as comprehensive extractives employment figures, in absolute and relative to total employment (6.3.d) for the year(s) under review.
     
  6. In accordance with requirement 7.1, the MSG must ensure that EITI Reports are comprehensible, actively promoted, publicly accessible and contribute to public debate. Key audiences should include government, parliamentarians, civil society, companies and the media. In accordance with requirement 7.1(e), the MSG should also ensure that outreach events, whether organised by government, civil society or companies, are undertaken to spread awareness of and facilitate dialogue about EITI Reports across country. The MSG should discuss the role the EITI could play in achieving national priorities and how it can generate public debate around natural resource use.
     
  7. In accordance with requirement 7.4iv-v, the MSG should ensure that future annual progress reports include an assessment of progress with achieving the objectives set out in the work plan including the impact and outcomes of the stated objectives, as well as a narrative account of efforts to strengthen the impact of EITI implementation on natural resource governance. This should include an overview of the multi-stakeholder group’s responses to and progress made in addressing the recommendations from reconciliation and Validation in accordance with Requirement 7.3

The MSG is encouraged to consider the other recommendations in the Validator’s Report and the International Secretariat’s initial assessment, and to document the MSG’s responses to these recommendations in the next annual progress report.

 

[1] For example, ISA 505 relative to external confirmations; ISA 530 relative to audit sampling; ISA 500 relative to audit evidence; ISRS 4400 relative to the engagement to perform agreed-upon procedures regarding financial information and ISRS 4410 relative to compilation engagements.

Background

Niger has been an EITI implementing country since 2007. Niger’s decision to implement the EITI was primarily intended to support the government’s efforts to diversify the economy away from its dependence on mining, for the benefit of citizens. Niger was accepted as an EITI Candidate on 27 September 2007, and the Niger EITI MSG was formally established by Prime Ministerial Decree 0073/PM on 4 July 2005. Niger was designated compliant under the EITI Rules in March 2011.

The Validation process commenced on 1 November 2016. In accordance with the Validation procedures, an initial assessment was prepared by the International Secretariat. The Independent Validator reviewed the findings and wrote a draft Validation report. Comments were received from the MSG. The Independent Validator reviewed the comments and responded to the MSG, before finalising the Validation report.

The Validation Committee reviewed the case on 28 August 2017. During these discussions, concerns were raised regarding Niger’s adherence to requirement 1.3 on civil society participation. The concerns related to incidents before the commencement of Validation (on 1 November 2016) and more recent events. The Validation procedure states that: “Without prejudice to the ability of the Board to exercise their discretion to consider all available evidence, the Secretariat should not take into account actions undertaken after the commencement of Validation”.

The Validation Committee requested that the Secretariat provide an updated assessment of requirement 1.3. The updated assessment (attached as an annex, below) concludes that the situation had deteriorated significantly between March and September 2017 and that Niger is no longer adhering to requirement 1.3. It recommended that “should the Validation Committee wish to exercise its discretion to consider events subsequent to the commencement of Validation, the International Secretariat recommends that Niger is found to have made inadequate progress on requirement 1.3”. The government and MSG were invited to comment. The Validation Committee reviewed the situation on 4 October, and agreed that, subject to considering the MSG’s comments, to recommend an assessment of “inadequate progress” on Requirement 1.3.

Based on the findings above, the Validation Committee agreed to recommend the assessment card and corrective actions outlined below.

The Committee also agreed to recommend an overall assessment of “inadequate progress” in implementing the 2016 EITI Standard. Requirement 8.3.c. of the EITI Standard states that:

ii.    Overall assessments. Pursuant to the Validation Process, the EITI Board will make an assessment of overall compliance with all requirements in the EITI Standard.

iii.   Inadequate progress. The country will be suspended and requested to undertake corrective actions until the second validation. For the suspension to be lifted, the country must in its second validation demonstrate at least meaningful progress.

The Validation Committee agreed to recommend a period of 18 months to undertake the corrective actions. This recommendation takes into account that the challenges identified are relatively significant and seeks to align the Validation deadline with the deadline for the 2016 EITI Report.

Scorecard for Niger: 2017

Assessment of EITI requirements

  • Not met
  • Partly met
  • Mostly met
  • Fully met
  • Exceeded
Scorecard by requirement View more Assessment View more

Overall Progress

MSG oversight

1.1Government engagement

There are regular, public statements of support from the government, a senior individual has been appointed to lead on the implementation of the EITI and senior government officials are represented on the MSG. There is evidence of government participation in EITI reporting, dissemination and outreach. The government has covered core funding for EITI implementation despite budget constraints.

1.2Company engagement

There is an enabling legal environment for EITI reporting and there do not appear to be legal barriers to company disclosure. Producing companies in the mining sector are actively and effectively engaged in the EITI process. There is no evidence of even informal consultations with oil and gas and exploration companies.

1.3Civil society engagement

Civil society representatives and journalists substantially engaged in the EITI process have faced arrests, coercion and reprisal between March and September 2017, while engaging in public debate on topics related to the EITI. These arrests fit a pattern of intimidation, harassment and arbitrary detention targeting civil society actors who petitioned the court to investigate allegation of corruptions in the extractive sector. Thus, the Board concluded that Niger has made inadequate progress on Requirement 1.3. In accordance with Requirement 3.3.c.i of the EITI Standard, Niger was suspended and given 18 months to undertake corrective actions. For the suspension to be lifted, the Government of Niger should ensure that the civil society protocol is fully adhered to, including ensuring that civil society representatives are able to engage in public debate related to the EITI process and express opinions about the EITI process without restraints coercion or reprisal.

1.4MSG governance

The MSG membership includes relevant actors from each constituency, although stakeholders agreed that the MSG’s structure should be revised to ensure relevant government and industry stakeholders are adequately represented. There is no evidence of constituency outreach ahead of MSG member selection and the nominations process has not been codified for any of the three constituencies. The MSG does not appear to have agreed its own ToR and the lack of revision of EITI Niger’s institutional structure and governance since 2008 is a concern, not least given the significant deviations in practice and the decrees’ lack of detail on nominations and internal governance. While decision-making appears to be based on consensus in most instances, stakeholders agree that there are no safeguards ensuring the inclusiveness of decision-making. Discussions at MSG meetings appear poorly documented in meeting minutes. While there is evidence of MSG input to key decisions related to EITI implementation, such as the ToR for the Independent Administrator, EITI Reports and workplans, there is no evidence of consultations with the broader constituencies about these decisions.

1.5Work plan

Publicly accessible and updated in a timely manner, Niger’s three-year EITI work plan includes some objectives aligned with the EITI Principles and national priorities, measurable and time-bound activities, activities aimed at addressing capacity constraints and some activities related to the scope of EITI reporting. Yet it does not include activities aimed at addressing any legal or regulatory obstacles, detailed plans for implementing recommendations from EITI reporting and Validation, while several activities appear to not be clearly time-bound or measurable. Meanwhile the sources of funding for activities in the work plan remain general and there is little evidence of stakeholder consultations in preparing the work plan beyond those directly represented on the MSG.

Licenses and contracts

2.2License allocations

The 2014 EITI Report did not provide a comprehensive list of extractives licenses awarded or transferred in 2014, nor a description of the process for transferring or awarding licenses, including the technical and financial criteria used as set out in Requirement 2.2.a. Non-trivial deviations from the applicable laws were not highlighted.

2.3License register

The excerpt of the mining cadastre included in the EITI Report was neither complete nor up-to-date. Licenses issued to SOPAMIN in December 2014, for example, were not included in the EITI Report. The list of valid permits in the petroleum sector in the EITI Report did not specify the dates of application, dates of award, nor the validity period of the license. Despite these weaknesses, significant progress has been made in bring transparency to the existing mining cadastre and efforts are underway to help modernise the cadastre system.

2.4Policy on contract disclosure

As contract transparency is mandated by the constitution, the government policy in theory is clear, but the EITI Report did not document the actual practice of contract disclosure. Contracts are not automatically published in the official journal as mendated by the constitution and it remains unclear how many contracts have actually been published.

2.1Legal framework

The MSG did not provide a summary of the fiscal regime applicable to the oil, gas and mining sector, including the level of fiscal devolution. Fiscal provisions included in contracts and conventions are not described in the Report. The Report did not explain the role and responsibilities of the relevant government agencies that have the mandate to manage the extractive sector.

2.5Beneficial ownership

Not assessed

The 2014 Report (Annex 2, pp.54-66) describes the MSG’s review of the legal ownership and disclosure mechanisms in Niger. The Report states (p.64) that disclosure of the beneficial owners of a company is required to incorporate a commercial company in Niger. This includes either civil identification for foreigners or copy of birth certificate for nationals. However there appears to be some confusion between legal (shareholding) and the actual beneficial ownership. The Report states that mining and petroleum cadastres will soon be online, which will partly address establishing a public beneficial ownership register, but it does not specify which information will be published in this online register.

2.6State participation

The EITI Report did not provide a comprehensive list of SOEs operating in the extractive sector, omitting CNEM, CNTPS, SML and SONICHAR that were all majority owned by the state in 2014. The EITI Report did not explain the financial relationship between these SOEs and the states, especially the rules and practices governing transfers of funds between the SOEs and the state, retained earnings, reinvestment and third-party financing.

Monitoring production

3.1Exploration data

The EITI Report provides an overview of the extractive industries, including exploration activities. This description could be more forward looking in future EITI reports, so as to provide more visibility in the sector’s potential and emerging governance challenges.

3.2Production data

Production volumes, disaggregated by commodity and by mining site have been disclosed, but not the values of commodities produced. The disclosed information was not clearly sourced and information on how production data was calculated was not disclosed in the Report.

3.3Export data

Total export volumes and the value of exports by commodity have been disclosed. The MSG has disclosed the sources of export data, but did not provide information on how export data was calculated.

Revenue collection

4.3Barter agreements

The TOR for the independant administrator adopted by the MSG on 24 June 2016 referred to a 90-million-euro project for the road Irhazere to be built by Areva that could potentially be classified as an infrastructure project (page 20). Yet the independant administrator states in the final report that the MSG is not aware of infrastructure provisions and barter type agreements. In the strategic partnership agreement signed in May 2014 between Areva and the Government of Niger, Areva committed to provide financial support for local development and infrastructure projects. This agreement was not covered in the EITI Report in accordance with Requirement 4.3.

4.6Direct subnational payments

The MSG did not provide a definition of materiality with regards to direct subnational payments. The International Secretariat received contradictory information that direct subnational payments exist and are considered material. Yet direct payments to local communities and the mechanism through which such payments are made have not been disclosed in the report. Stakeholders appeared confused between direct subnational payments and subnational transfers. The confusion between these two payments has hindered transparency on both issues instead of improving it.

4.7Disaggregation

The Report provides disaggregated figures by revenue stream and by company.

4.9Data quality

The work completed by the Independent Administrator deviates significantly from the approved TOR and lacks strong quality assurance procedures. Disclosed payments and revenues were not certified and there is evidence that only 27% of disclosed payments came from audited accounts. All contextual information was prepared by the MSG, some of which was not clearly sourced.

4.1Comprehensiveness

The MSG did not define materiality thresholds for selecting companies and revenue streams specifically for the 2014 EITI Report. Rather, it followed the approach adopted in 2010, prior to the adoption of the EITI rules and the EITI Standard. Lack of a clear definition of materiality is compounded by a lack of an exhaustive list of companies operating in the country and lack of full disclosure from government agencies. The EITI Report did not include an assessment of the materiality of non-reporting.

4.2In-kind revenues

Not applicable

The MSG concluded that in-kind revenues were not material. Based on a review of the pricing mechanism of various mineral products and stakeholder consultations, the International Secretariat agrees with the MSG assessment that in-kind revenues of oil, uranium and gold were not material in 2014.

4.4Transportation revenues

Not applicable

The MSG did not agree a definition of materiality with regards to revenues from transport, but based on stakeholders’ consultation during the fact finding mission, the Secretariat concludes that transport revenues were immaterial during the reporting period.

4.5SOE transactions

Only one SOE (SOPAMIN) out of five reported transactions as an SOE. CNEM, CNTPS, SML and SONICHAR are all majority owned by the state but were not classified as SOEs. These SOEs made material payments to the government, but the EITI Report did not explain whether they collected material revenues on behalf of the state.

4.8Data timeliness

The 2014 Report was published in November 2016, which meets the timeliness requirement. The MSG approved the reporting period and cash-accounting basis of EITI reporting.

Revenue allocation

5.1Distribution of revenues

The Report indicates that all revenues from the extractive industry are recorded in the national budget. The MSG gives information about distribution of revenues in theory not in practice. Revenues not recorded in the national budget were not clearly identified for the fiscal period covered (p.23). The report did not reference national classification systems.

5.2Subnational transfers

The MSG described the legal framework of revenue sharing requirements in the mining and petroleum codes, but it did not disclose any material payments in 2014. The MSG did not establish whether the 15% of statutory subnational transfers were material during the reporting period. It did not require relevant government agencies (DGI, DGTCP, regions and municipalities) to disclose such information and the MSG’s definition of materiality regarding mandatory subnational transfers remains unclear

5.3Revenue management and expenditures

Not assessed

The MSG has made some attempt to including information on the budget-making process in the EITI Report.

Socio-economic contribution

6.1Mandatory social expenditures

The MSG did not define materiality with regards to mandatory social expenditures. Despite, partial disclosure of social payments by two companies, there is no evidence that mandatory social expenditures have been disclosed and reconciled in accordance with EITI Requirement 6.1.

6.2Quasi-fiscal expenditures

The MSG did not define materiality with regards to quasi-fiscal expenditures by SOEs, including SOE subsidiaries and joint ventures. The MSG gave a long list of activities completed by SOPAMIN without stating the cost of these activities.

6.3Economic contribution

Estimates of the sector’s contribution to the economy did not include local coal consumption. Only nine companies disclosed employment figures and the sector’s contribution to the government’s budget is not always reliable.

Outcomes and impact

7.2Data accessibility

Not assessed

Some of Niger’s EITI data is available in machine readable format through the EITI global website albeit not for its latest EITI Report covering 2014. EITI data is not accessible on the EITI Niger website.

7.4Outcomes and impact of implementation

The MSG has reviewed progress and outcomes of implementation on a regular basis, including by publishing annual activity and progress reports over the past three years. However, the 2015 annual progress report focused more on outcomes than on impact and the overall impact of EITI Niger remains unclear.

7.1Public debate

EITI Niger has ensured that the EITI Reports are accessible to the public, albeit primarily online, and contribute in a limited manner to public debate in the capital and in some extractives regions. While CSOs have driven dissemination and outreach efforts in the past, the slowdown in dissemination and outreach since 2015 is a concern. Accessibility of EITI data beyond the capital Niamey remains weak. Stakeholders affected by mining activities in rural areas are not involved in EITI implementation.

7.3Follow up on recommendations

The MSG and the government have taken steps to act upon lessons learnt, to identify, investigate and address the causes of any discrepancies and weaknesses of the EITI process and to consider the recommendations for improvements from the Independent Administrator.

Países
Niger